Municipality / City: TOLOSA


 

Project Title: Datum: Monday, 12 May 2014 14:58
Province: LEYTE
Region: VIII
Project Description:

RISK RATINGHigh

Risk Trigger

Risk TriggerRisk RatingRisk ResponseResponsibility

Physical slippage

by 10% for 1st Q

   Require LGU/ contractor to implement procurement plan and do advance purchase  

Disbursement fell 

below 10% for 1st Q

   Require contractor to submit quarterlybilling 15 days after last day of each quarter  

Risk Monitoring Matrix 

Risk CategoryRisk TriggerRisk RatingStatusResponse Action

Responsibility

and Milestone Check

 Physical 

Physical slippage

by 10% for 1st Q

  

Delayed delivery of construction materials for 1st Q

Require LGU/ contractor to implement procurement plan and do advance purchase MLGOO

Monthly monitoring

Financial

Disbursement fell 

below 10% for 1st Q

  

Delayed submission of contractor’s billing

Require contractor to submit quarterlybilling 15 days after last day of each quarter  

Risk Status Report 

Risk CategoryRisk IssueStatus / CommentRecommendation for Inaction

 

Physical

LGU/contractor unable to deliver construction materials on time for 3 consecutive months

Closed - All materials successfully procured

 

Suspend contract - if no positive action taken for 2 quarters; plus apply penalty clause provision

or

Cancel = for 3 quarters

Financial

Contractor unable to submit quarterly bill as scheduled

Closed - Disbursement monitored and regular report submitted

 

Impose penalty clause provision – if billing for next Q is delayed