RISK RATING: High 
| Risk Trigger | Risk Rating | Risk Response | Responsibility | 
|---|---|---|---|
| Physical slippage by 10% for 1st Q | Require LGU/ contractor to implement procurement plan and do advance purchase | ||
| Disbursement fell below 10% for 1st Q | Require contractor to submit quarterlybilling 15 days after last day of each quarter | 
| Risk Category | Risk Trigger | Risk Rating | Status | Response Action | Responsibility and Milestone Check | 
|---|---|---|---|---|---|
| Physical | Physical slippage by 10% for 1st Q | Delayed delivery of construction materials for 1st Q | Require LGU/ contractor to implement procurement plan and do advance purchase | MLGOO Monthly monitoring | |
| Financial | Disbursement fell below 10% for 1st Q | Delayed submission of contractor’s billing | Require contractor to submit quarterlybilling 15 days after last day of each quarter | 
| Risk Category | Risk Issue | Status / Comment | Recommendation for Inaction | 
|---|---|---|---|
| 
 Physical | LGU/contractor unable to deliver construction materials on time for 3 consecutive months | Closed - All materials successfully procured | Suspend contract - if no positive action taken for 2 quarters; plus apply penalty clause provision or Cancel = for 3 quarters | 
| Financial | Contractor unable to submit quarterly bill as scheduled | Closed - Disbursement monitored and regular report submitted | Impose penalty clause provision – if billing for next Q is delayed |